WP3.1: Developments in Production of Gas: course of integrated management of reservoir
THE AIMS
The modern attitude to the optimal development and natural gas reservoir exploitation assume process called "Integrated Reservoir Management". In this term are included various multidisciplinary aspects: seismic and well logging integration, geology model iteration, well testing interpretation, reservoir production simulation, completion of wells, gas gathering and processing, material balance analysis, water conning control etc.
The target of this work package (fig. 3.2) is:
- To learn and show how to manage various type of information, how to integrate various experts into one "RESERVOIR TEAM".
- To increase engineers' knowledge of other discipline aspects to allowing wide communication with specific geology, drilling and exploitation experts,
- To increase personal creativity
- To fully understand reservoir's physics by using an innovative technique

Fig. 3.2 Mind map of content of WP1 course
The role and the tasks of each partner involved
- P8: Co-ordination of task.. Set up of input data to course WP3.2,WP3.4.
- P1,P2,P8: Work in the WP3.1
The start and finish dates and overall duration
The overall duration of work package: 428 days.
The working methods and techniques
The selection of technical material, concerned topics of course and conversion into multimedia material ready to publish in Internet, on CD etc.
The expected outcomes/results of the work package
The main outcome is prototype of multidisciplinary course
Dissemination ways
Responsible P4: Preparing web server, forum of experts on web, CD's with announcements of course, folders and brochures, articles on topics at regional vocational conferences, workshops with outside gas experts, articles in regional press.